Fall 2016 Facilities Master Plan Update

HIGH PRIORITY PROJECTS

- Physical improvements for all projects are complete and within budget.  Final software programming and commissioning for security system in in process and should be complete by the end of the year.

HILLSIDE ELEMENTARY SCHOOL

- Changes for the 2016-2017 school year include security upgrades, reinforced area of refuge in corridor, partial administration renovation, stage lift for ADA accessibility, new coiling door in kitchen and new exterior soffit.

LOVELAND ELEMENTARY SCHOOL

- Changes for the 2016-2017 school year include security upgrades, new area of refuge and cafeteria tables.  We are currently looking at land acquisition options for building replacement.

OAKDALE ELEMENTARY SCHOOL

- The new Oakdale Elementary is on budget and on schedule to open in January 2018.  Students are currently using the Swing School, newly renovated for this school year.  Changes include a security entrance vestibule, ADA upgrades, new area of refuge, electrical and security system improvements and new fire sprinklers.  Footings are expected to be in place by mid November, and the building shell should be up by the holiday break.

PADDOCK ROAD ELEMENTARY SCHOOL

- Changes for the 2016-2017 school year include security upgrades, new areas of refuge, a new fire alarm system, new boiler, settlement repairs, and soffit and siding repairs.

ROCKBROOK ELEMENTARY SCHOOL

- Changes for the 2016-2017 school year include security upgrades, new area of refuge, stage lift for ADA accessibility, new administration area and art/music classroom.

SUNSET HILLS ELEMENTARY SCHOOL

- Crews began moving soil from Oakdale to Sunset Hills September 26, a move that will save approximately $250,000 and last for one month.  Project Advocates is finishing Design Development and in on track to procure a general contractor.  Construction will begin Spring 2017 with the new building expected to open in August 2018.  The design proposal will go before the Board of Education at the October 17 meeting.  A public committee will then be formed to share insight and collaborate on the building as construction moves forward.

SWANSON ELEMENTARY SCHOOL

- Project Advocates is in the process of selecting an architect, with design beginning this fall.  11 proposals were submitted, entries narrowed to 5 by mid-October. The final construction schedule will be determined based on Swing School utilization.

WESTBROOK ELEMENTARY SCHOOL

- Changes for the 2016-2017 school year include security upgrades, stage lift for ADA accessibility, new boiler, 2-way valves at unit ventilators, area of refuge improvements, new administration area and new classrooms.

WESTGATE ELEMENTARY SCHOOL

- Changes for the 2016-2017 school year include security upgrades, cafeteria tables and a stage lift for ADA accessibility.

WESTSIDE MIDDLE SCHOOL

- WMS is on track for phased completion with the new addition of 13,000 square feet opening in January 2017.  Final project is slated to be complete in August 2018.  

 

***

For complete plans and timelines, click on Renovation Details and choose the building you would like to learn more about.