Progress

Prairie Lane Construction Update, September 2019

As of September 9, 2019 abatement work is complete and project leaders have received final inspections. Fencing is currently being installed at the site, and openings are being secured in the portion of the building that will remain. Demolition will begin on the south side of the building later this month after project leaders receive necessary permits.

Westside has contracted with Armored Knights to provide monitoring services at the site from 8:00pm to 4:00am nightly. This security team will monitor the perimeter of the building and grounds.

Officials will also be monitoring bus pickup for Westside Middle School students at the site. If you or your students have problems or concerns, please reach out to Student Services at 402-390-2107.

For the latest Design Development Plan at Prairie Lane Elementary School, click here.