Progress

September Progress Update at Sunset Hills

Sunset

Vrana Construction crews continue to work at Sunset Hills Elementary as part of Westside’s Major Facilities Plan, with a tentative completion date set for August 2018. CLICK HERE for an aerial video highlighting progress at the site.

 

For the month of September:

-       Families who attend or live nearby Sunset Hills should expect concrete block delivery trucks accessing the site through the neighborhood to deliver heavy equipment as well as roofing materials.

-       Final steel deliveries are taking place this month; neighbors and families at Sunset should expect flat-bed delivery trucks as steel is transported to the site and installed, as well as crane mobilization and operation. Neighbors should also expect construction dumpster delivery and haul away.

-       Sewer work is now complete on the west side of the site near the pool. Concrete will be replaced in the west parking area.

-        Most delivery and construction trucks will access the site on 94th Street from Pacific. Other traffic may use 96th Street because of the traffic light at Pacific.

Questions? You can contact the Project Advocates team at rob@project-adovcates.com or joel@project-advocates.com.