May Construction Updates

We have great news to report from the home of the future Prairie Lane Elementary! Crews have been hard at work without disruption, as it is easier to maintain social distancing guidelines on most job sites.

The steel frame for most of the building is nearly complete, and the last portion of the building frame to be constructed is the new gym on the northeast side of the site. The masonry walls and steel roof should be completed in early June. Exterior wall framing and roofing work will begin in the coming weeks. Plumbing, HVAC and electrical rough-in work, along with concrete slab on grade, are the next activities inside the building footprint. Work to construct the area at Hascall St. will begin in late May and run through June.

Thank you all for your engagement and support as we continue our work on this exciting project!